Shell MetOcean

Client:

Shell

Budget:

$217,088

Location:

Robert, LA

Type of Work:

Demolition, Pond Excavation, Site Fill, Utilities

Scope of Work:

Under extremely wet conditions, Durr assisted Shell's MetOcean plant with their expansion efforts.

Work included concrete demolition, pond excavation, site fill, underground drainage and installation of a Bentonite pond liner for the newly dug pond.

After all the pipes were laid and fill material was added for the building pad, Durr concentrated their efforts on the newly dug pond.  They placed a Wyoming Bentonite pond liner that weighed over 72,000 lbs. and sealed the 76,000 sq. ft. pond surface.

 